Kennesaw Avenue COA: A Homeowner's Start-to-Finish Guide

The Kennesaw Avenue COA is the permit before the permit. Kennesaw Avenue was Marietta's first locally designated historic district (August 2013). If your project is covered by the ordinance, a Certificate of Appropriateness comes before your building permit — here is the whole process.

Kennesaw Avenue COA: A Homeowner's Start-to-Finish Guide

First: is your home actually in a local district?

Marietta lists five National Register districts (Atlanta-Frasier, Church-Cherokee, Northwest Marietta, Washington Avenue, Whitlock Avenue) — but National Register listing alone does not impose a COA on a private owner. Local designation does. Kennesaw Avenue (2013) is the confirmed first local district; Forest Avenue is also presented by the City as a local district. Confirm your parcel with Marietta Planning & Zoning before assuming either way.

The Kennesaw Avenue COA process

  • Read your district's design guidelines before designing
  • File a complete application with all street-visible elevations — incomplete applications are not forwarded to the Historic Preservation Commission
  • Public hearing; notice is mailed to the owner, occupants and adjacent owners
  • The Commission approves or rejects within 45 days of filing
  • Building permits are not issued without proof of COA; approved work must start within 3 years; demolition additionally requires City Council approval

What this means for your renovation

Budget the COA into your timeline (it leads the City permit, which runs through SagesGov at $4 per $1,000 plus $50). Design additions to be compatible and subordinate. And treat any contractor who says 'we'll just pull the permit' for a Kennesaw Avenue exterior as a red flag. Our historic renovation page covers the craft side.

A realistic COA timeline, using a real permit example

Work backwards from your hoped-for start date. The Historic Preservation Commission has up to 45 days from filing to approve or reject a complete application, and an incomplete one is not forwarded at all — so the elevations and district guidelines come first, the hearing second, and only then the building permit. On fees, a city example keeps expectations honest: a $60,000 exterior project inside Marietta carries a $290 residential permit fee at $4 per $1,000 plus $50, filed through SagesGov once the COA is in hand. Approved work must start within 3 years, and demolition follows a separate path requiring City Council approval as well — which is why, on Kennesaw Avenue, the design conversation should begin a full season before the construction conversation. Keep a dated copy of the approval with your permit set, because inspectors and future buyers may both ask for it.

Talk through your Marietta project

Call for a walkthrough, a written scope, and a budget range grounded in dated Marietta and Atlanta market guides — not a mystery number.

2575 Delk Rd, Marietta, GA 30067 · Monday–Saturday: 8:00 AM – 6:00 PM · Sunday: Closed

Contact Golden Hammer Home Renovation

Call (404) 594-2939 Monday–Saturday, 8:00 AM–6:00 PM. Tell us the room or project, your neighborhood, and whether your address is inside Marietta city limits or unincorporated Cobb County — that one detail decides who permits the work. Sunday: closed.